Accomplishments for 10/14-10/15

Tyler and I made some more headway this weekend. We finished the following:

  1. Replaced the floor joists under the old red bathroom.
  2. Sealed up the attic doorway with new joists.
  3. Removed the last wall for the stairway to the attic.
  4. Laid down the new subfloor over the new floor joists.
  5. Pulled down the remaining nails from the joists above the opening for the spiral staircase.
  6. Swept down the cellulose insulation from 50% of the second floor in prep for electrical work.
  7. Removed debris from the master bedroom, master bathroom, master closet and shared bathroom area.
  8. Finalized the floor plan for the second floor master bathroom, master closet, laundry room and shared bathroom.
 

What did you think of this article?




Trackbacks
  • No trackbacks exist for this post.
Comments
  • No comments exist for this post.
Leave a comment

Submitted comments are subject to moderation before being displayed.

 Enter the above security code (required)

 Name (required)

 Email (will not be published) (required)

 Website

Your comment is 0 characters limited to 3000 characters.