Progress Update
I thought it was about time that I update everyone on the current state of renovations. Currently, all renovations have been limited to the second floor. These renovations include:
- All demolition work has been completed.
- Rough framing of walls between rooms has been completed.
- All electrical runs have been made to the basement.
- Master Bathroom electrical rough-ins have been completed.
- Shared Bathroom electrical rough-ins have been completed.
- Master Closet/Laundry electrical rough-ins have been completed
- Foyer electrical rough-ins have been completed.
- New roof installed.
- New vent stack run.
The following renovations still need to be completed before inspections:
- Electrical rough-ins need to be completed.
- SE Bedroom
- SW Bedroom
- HVAC layout and installation
- Plumbing
- Install ladder to attic.
- Install windows.
Once that work is completed and the inspections are over, Tyler and I can have the insulation installed. Then, it's time for drywall!